Docs: Record the milestones and the reasoning behind each date - #15
Merged
Merged
Conversation
The maintainer asked for a completion date per milestone. M1 (real package and rule-based re-export) is 2026-10-16: the binder contract landed and what is left is pure Python. M2 (notebook widgets) is 2026-11-13: it needs JVM render proofs, a broken Gradle cache link, the TextFieldState check and three INTENT questions decided. M3 (wheel with stubs and manifest) is 2026-11-27: stubs need only M1, but final names settle in M2. documentation corrected: PROJECT.md gains the milestone table. Tests unchanged: 40 passed, 37 skipped without a PythonMultiplatform checkout. Refs #14
This file contains hidden or bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Add this suggestion to a batch that can be applied as a single commit.This suggestion is invalid because no changes were made to the code.Suggestions cannot be applied while the pull request is closed.Suggestions cannot be applied while viewing a subset of changes.Only one suggestion per line can be applied in a batch.Add this suggestion to a batch that can be applied as a single commit.Applying suggestions on deleted lines is not supported.You must change the existing code in this line in order to create a valid suggestion.Outdated suggestions cannot be applied.This suggestion has been applied or marked resolved.Suggestions cannot be applied from pending reviews.Suggestions cannot be applied on multi-line comments.Suggestions cannot be applied while the pull request is queued to merge.Suggestion cannot be applied right now. Please check back later.
Closes #14
Adds a milestone table to PROJECT.md matching the GitHub milestones (M1 2026-10-16, M2 2026-11-13, M3 2026-11-27, issues #7–#13), with one line of reasoning per date.
Documentation corrected: PROJECT.md. Tests are unchanged: 40 passed, 37 skipped without a PythonMultiplatform checkout.